I was currently employed with Eden Apparels (edenrobe) Pvt Ltd.
I have 13 Years Experience in Civil Engineering Fields.
I have done BSc Civil Engineering from Swedish RYK
Registered Engineer by PEC (Level ll)
Affiliated By UET Lahore
Works Experience in
Grid Station & Transmission Line, Power Plant Construction and Commercial Building.
PROFESSIONAL SKILLS & EXPERTIES
Office works (IPC, BOQ, BBS, and Rate of analysis, Material Reconciliations,
EOTs and Claim invoice by Contractor, Progress Reports).
Software (AutoCAD, Primavera, MS Excel, Plan swift)
Site Execution & Management (layout, site surveys, reinforcements, formwork ,
Field Site Test and Documentation.)
QA/QC Management works Experience.
Strong study of drawings, BOQ, specifications and Contract.
Inspections at site checked works according to Drawing
and BOQ Specification.
Maintain and manage project related data.
Control over costs that project is delivered in allocated budget.
Prepared Detailed Cost estimation, BOQ, Physically site Measurements
sheet, feasibility Reports.
Prepare progress reports for Finished Project in given timeline.
Planning and Scheduling of project for monitoring the Progress of site.
Monitoring and checked material costs demand &materials
Reconciliation Reports
Dealings with Consultants, Project Designer, Architect,
and Contractors Reviews Drawing and other Technical issues.
Project Planning, Estimations and Project Scheduling related software
knowledge and Command.
Project: ACE Max Shopping Mall (R.Y.KHAN )
ACE Galleria Shopping Mall (BAHAWALPUR)
Managed all types of construction activities.
Verified Site Bills & Material Demand. Managed and Control
Over cost and Delivered Project within Actual budget.
Monitor the project progress According work schedule and
ensure quality of the works executed by Specification.
Preparing (BOQs) & nomenclatures. Billing, Price Variation
and Estimation including Analysis of Rates.
Maintain cashbook, & Control Cash Record and other
Project related Data.
Dealings with Consultants, Project Designer, Architect, and
Contractors regarding is Reviews Drawing and other
Technical issues.
Project:
Ø 132/11.5kv (GIS) Grid Station Rahim Yar Khan
Ø Eight 220kv and 500kv Grid Station Extension and Augmentation works
Civil works Inspection, Verifying BBS, Rate of Analysis, Progress Report, Invoices, cost Claims by Contractors, (EOTs) and Inspection on site that Contractors are following Quality and Safety Standards Site.
Managed All Project related Data, Documentation, meeting record, Contactors agrements and invoice record. Resolved Contractor site issues. Managed inspections (IRs) of (Layout, Formwork, Reinforcement, & Concrete Pouring) and prepared records & documentation. Performed, Supervised, and Monitored quality tests of materials, projects-related products, and equipment.
Perform All the construction duties at site. Approved & Inspection (IPC, BBS, MS, MIR, IR, RFI,MOM)
Managed all types of construction activities.
Project:
Ø WHR 7.5MW POWER PLANT Project ACL WAH.
Ø WHR 12 MW POWER PLANT Project ACL NIZAMPUR
Prepared (MAS, MIR, IR, CCO, MOM, (DPR& WPR), BBS, IPC and maintaining record of Documents.
Project:
Ø 500kv Grid Station SHIKARPUR
Ø 220KV Grid Station LORALAI
Ø 500/220/132 KV Grid Station & 500KV/220KV Transmission line DG Khan
Transformer foundation, Gantry Foundation, U/G Trenches Manhole, Dyke Wall, Fire wall, Grouting Steel Structure, Walk way & Control Buildings, Offices, and Allied works.Close monitoring and Inspection of major activities (Layout, excavation, shuttering works, rebar works, concreting, embedded items/anchor bolts, waterproofing, Grouting and backfilling.